Ft. Bliss – Sheridan Water Loop Phase II

Project Description

Client:   Ft. Bliss Water Services
Location:   Ft. Bliss, Texas

Scope of work included installation of over 5000 ft of 12″ waterline, jack and boring of existing main thoroughfare, curb and paving, and landscape.

UTEP University Housing Phase III – Site Work

Project Description

Client:  El Paso Water Utilities
Location:   El Paso, Texas

Scope of work included installation of approximately 3900 linear feet of 60-inch sewer pipe, 320 linear feet of 90-inch steel casing by jack/bore, manholes, junction box, base course, asphalt, 60-inch by 54-inch tie-in, dewatering, traffic control, and trench safety.

Eastside Interceptor Phase 5 Part 2

Project Description

Client:  El Paso Water Utilities
Location:   El Paso, Texas

Scope of work included installation of approximately 3900 linear feet of 60-inch sewer pipe, 320 linear feet of 90-inch steel casing by jack/bore, manholes, junction box, base course, asphalt, 60-inch by 54-inch tie-in, dewatering, traffic control, and trench safety.

EPE Rio Grande Power Plant Sewer Improvements

Project Description

Client:   El Paso Electric Company
Location:   El Paso, Texas

Project consists of pipe installation, manholes, cleanouts, steel casing installation, relocation of asbestos cement waterline, removal and replacement of HMAC, 2-sack flowable fill and geotextile fabric.  Work also includes preconstruction recording, traffic control, bypass pumping, dewatering, trench safety, and removal and disposal of existing manhole and sewer line.